Display the Schedule Realism Advisor Dialog Box

Use this dialog box to change settings and run the advisor.

To display the Schedule Realism Advisor, complete the following steps:

  1. Select the S1 // Projects tab.
  2. In the Projects pane, select the project.
  3. In the Scenario Generation group, click Schedule Realism Advisor. The Schedule Realism Advisor requires a scenario. If you do not have one when you click the icon, a message displays asking if you want to create a new scenario.

    If you have a scenario, or after one is created, the Schedule Realism Advisor displays.